How to utilize all gantt

All gantt in ProofHub offers a clear and detailed overview of task advancement across multiple projects, bringing transparency and clarity to your workflows.

  1. Click on “Everything” and select “All gantt”.
  2. In the “All gantt” view, you will see a list of all tasks on gantt from all your projects.

Filters

Click on the filter icon at the top-right corner of the page.

Projects: You can select one or multiple projects to display in the gantt view and click “Apply”.

Assigned: You can select a specific person or all team members to view their tasks in the gantt view click “Apply”.

Export

There are two ways you can export the gantt in ProofHub.

  1. Click on the three dots icon at the top-right of the page.
  2. Select “Print” to print the gantt chart.
  3. Or else, download the gantt chart in PDF format by choosing the “Export as PDF” option. 

Note: If you can’t fit the gantt chart on one screen while exporting/printing, then try changing the settings as follows:

  • Change the DPI to “200
  • Select the orientation to “Landscape
  • Select the paper format to “A3

Need more help?

- Can't find the answer to your questions? Contact ProofHub Support
- You can also book a demo.